Table 1 Existing capacities, allowable capacity expansion and generating efficiency for all facilities

From: An interval mixed-integer non-linear programming model to support regional electric power systems planning with CO2 capture and storage under uncertainty

Electricity generation facilities

Existing Capacity O i (GW)

Upper bounds of capacity expansionEmax it (GW)

U it (PJ/GW)

t = 1

t = 2

t = 3

t = 1

t = 2

t = 3

PC (i = 1)

5.5

[1.5, 1.7]

[1.2, 1.5]

[1.0, 1.2]

[90, 95]

[95, 100]

[100, 105]

NGCC (i = 2)

2.5

[0.9, 1.3]

[0.8, 1.2]

[1.0, 1.3]

[80, 88]

[85, 92]

[90, 96]

IGCC (i = 3)

1.5

[2.0, 2.3]

[2.5, 3.0]

[3.0, 3.5]

[95, 100]

[100, 107]

[105, 110]

Hydro power (i = 4)

0.5

[1.5, 1.8]

[2.0, 2.5]

[2.2, 2.6]

[70, 75]

[75, 80]

[80, 85]

Wind power (i = 5)

0.2

[2.0, 2.5]

[2.2, 2.8]

[2.5, 3.0]

[20, 24]

[30, 34]

[35, 38]